The Airport Next Door Goes Quiet in April: How McLain Flats and Starwood Will Travel Through 2027

Aspen/Pitkin County Airport closes on Sunday, April 4, 2027, at 11 p.m. and reopens on Friday, Nov. 19, 2027, at 7 p.m. For seven and a half months there will be no commercial or general aviation flights and no access to the terminal. Helicopters are grounded too. Most of the valley will feel that as a longer trip to the airport. In McLain Flats and Starwood, the airport is a near neighbor, so the change runs both ways. The runway goes quiet while a heavy construction project runs six days a week beside Owl Creek Road. Getting out of the valley also stops being a short drive and starts to depend on the calendar, because the main replacement airport is on the far side of a canyon that will be under repair for most of the same months.

The first changes arrive before the snow.

Owl Creek Road Gets Its New Shape This Fall

The enabling work along Owl Creek Road is almost finished. Crews have moved power and communications lines with Holy Cross, Lumen and Comcast, put in a new waterline, and started retaining walls for the relocated stretch of road. In mid-September, the Owl Creek Trail moved to a temporary alignment that was expected to last about six weeks, with extra fencing to keep trail users apart from the work zone.

Here is what is left on the fall schedule, in order:

  1. A shoulder closure on Highway 82 near the airport stays in place through most of October.
  2. Crews plan to pave parts of Highway 82, Owl Creek Road, Owl Creek Trail and the Airport Operations Center parking lot from October 28 to 30, with lane closures on those days. The airport says the dates depend on weather.
  3. By November, Pitkin County expects Owl Creek Road and Trail to be back to two lanes in their new configuration.

The Highway 82 lane closures that ran from Sept. 28 to Oct. 10 prepared a temporary construction entrance at the downvalley end of the airport. That entrance is meant to cut traffic impacts once the runway work starts next spring. In practice, the entrance most McLain Flats and Starwood drivers pass every day is being rebuilt around a jobsite that will be far busier by May.

April 4 to November 19: Where the Flights Go

The runway is being rebuilt, widened and shifted to meet current FAA design standards. The airport's closure travel page lists four other airports and measures each drive to Brush Creek Park & Ride. The airline details for Eagle come from Aspen Times reporting covered in the next section.

Airport Distance to Brush Creek Drive time listed Service during the closure
Eagle County Regional, EGE 67 miles 1 hour 35 minutes Expanded American and United schedules
Rifle Garfield County, RIL 65 miles 1 hour 30 minutes Private aviation, Atlantic Aviation FBO, planned AERO charter
Grand Junction, GJT 126 miles 2 hours 15 minutes Existing commercial service
Denver International, DEN About 200 miles 3 hours 45 minutes Existing commercial service

Eagle and Rifle are almost the same distance away. Eagle is the one gaining scheduled flights, and from May through October the drive from Eagle runs into roadwork.

Eagle Carries the Flights, and the Canyon Narrows

According to the Aspen Times, Eagle County Regional is set to go from 46 weekly flights in peak summer 2026 to 112 in summer 2027, well over double. Starting May 27, 2027, American plans to add a fourth daily flight to Dallas/Fort Worth, two daily Los Angeles flights and one daily flight to Chicago O'Hare. That takes its Eagle schedule from 21 weekly flights from one hub to 49 from three. United plans to double its Denver service from three to six daily flights. It will also move Houston and Chicago from weekends only to daily and add daily summer service to Los Angeles, for a total that grows from 25 weekly flights to 63. Delta is the third of Aspen's major carriers, and as of Oct. 8, Airport Director Diane Jackson said it had not yet announced any added Eagle service.

Those added flights land on the far side of Glenwood Canyon. The Aspen Daily News reported that from May through October 2027, the Colorado Department of Transportation will make critical repairs to the road, bridge, structural rail and tunnel between No Name and Hanging Lake. Traffic in both directions will share single lanes on the westbound side while crews work on the other side. CDOT communications manager Austyn Dineen told the paper the work is part of a multi-season effort that "cannot be deferred despite upcoming airport closures without pushing crucial work out several years."

The same article shows where the schedule gives way. CDOT expects to put traffic back to one lane in each direction from Friday through Sunday, with no active work and no traffic stops on weekends. The busiest summer Eagle has ever planned and the canyon's head-to-head pattern will overlap Monday through Thursday. On weekends, someone flying into Eagle drives home through a canyon running in its usual configuration.

Rifle Becomes the Private Gateway

For private aircraft, the closure's main alternative is Rifle. The airport lists Rifle as a general aviation airport served by an Atlantic Aviation FBO, with AERO jet charter service planned for summer 2027.

On Oct. 12, NetJets announced a new Rifle complex with a 6,000-square-foot private terminal and an aircraft hangar, expected to be running by early 2027. The release names the Aspen runway closure as the reason Rifle will serve as a gateway. Eagle remains an option for private aircraft as well. In July, Eagle's aviation director told the Aspen Daily News he was working with the airport's FBO on a plan for private jet parking and did not expect capacity problems.

During the closure, the airport's FAQ tells helicopter operators to ask Glenwood Springs or Rifle about parking.

The Eagle Shuttle Is Still a Plan

The Community Continuity Planning Group includes Pitkin and Eagle counties and local stakeholders. Its first priority is ground transportation between the upper valley and Eagle. According to the Aspen Times, RFTA has started a request-for-qualifications process for shuttle service from Eagle and Denver, with a target fare of about $50. The projected $600,000 subsidy would be split, half from the Elected Official Transportation Committee and half from partners. ACRA, RFTA and Aspen One have tentatively offered to contribute. County Manager Kara Silbernagel explained the need for a subsidy to the paper this way: "If there was a free-market solution, a private solution, it would already be happening."

The group hopes the low fare will keep rental cars from flooding the valley. Shuttles to Eagle could start as early as this ski season, which would give the route a trial run before the runway closes. So far there is no published timetable, route map or booking system. For trips without a car, the airport points to services that already run. Bustang travels between Denver and Grand Junction with a stop in Glenwood Springs, and Amtrak also stops in Glenwood. RFTA connects up the valley from either one.

Next Door, Six Days a Week

The runway goes quiet in April, but the land around it gets busier. In June, contractor Kiewit told the Aspen Daily News that the public should think of the rebuild as a 24/7 operation. Its plan calls for six workdays a week, Monday through Saturday, with Sundays held as makeup days. The groundwork is already in place. There is a reinforced haul road from Owl Creek to the hay fields and office area, an office trailer yard downvalley from the Airport Operations Center, and a batch plant area being prepared for next year. Stockpiling has started on the west side, some of it at night. Building the stockpile now is meant to reduce truck trips in 2027. The Aspen Times also reported plans to keep construction traffic away from the Highway 82 and Owl Creek Road intersection when possible and to house workers close to the project. Water trucks are handling dust for now, and the airport is coordinating revegetation and winter dust measures.

The terminal project runs longer than the runway work. On Oct. 14, Pitkin County commissioners unanimously approved a lease that turns Lot A, at the south end of Brush Creek Park & Ride, into a temporary rental car facility from Jan. 1, 2027, through Dec. 31, 2030. Deputy County Manager Ryan Mahoney told the Aspen Times that terminal construction will last through 2029 and that demolishing the old terminal could run into 2030. He also said traffic in and out of the facility "is expected to be low."

The funding is coming in as planned. On Sept. 28, ASE received a $37 million FAA grant for runway construction, the largest single grant in its history. The whole airfield program is budgeted at about $269 million, and the airport expects more than $213 million in federal funding over the life of the project. Neighbors who want updates as the work happens can call the construction hotline at 970-920-5284, sign up for the Frequent Flyer Updates, or check aspenairport.com/construction. The airport says it returns voicemails within 24 hours.

If you own on McLain Flats or in Starwood and want to talk through how the 2027 construction year fits your plans for the property, I'm glad to help. Soffia Wardy watches this corner of the valley closely and can tell you what is happening down the road. Let's Connect.